What is this about?

The draft Bill proposes amendments to the Land Use Planning and Approvals Act 1993 (the LUPA Act).

The draft Bill is in response to a Magistrate’s ruling on DPP v Recycal Pty Ltd [2026] TASMC 02 (the Magistrate’s decision) on the interpretation of section 53(4) of the LUPA Act that a planning permit is not in effect until all approvals associated with the proposed use and development have been granted.

What is not included?

The draft Bill does not change the planning scheme rules that development applications are assessed against.

Who is involved?

The SPO is the lead agency in the project. Parliament makes the final decision on changes to legislation.

How long will it take?

The aim is to lodge a draft Bill with Parliament in early 2027, after the public consultation ends and all submissions received have been carefully considered.

Background

Section 53(4) of the Act states:

Where any other approvals under this Act or any other Act are required for the proposed use or development to which the permit relates, the permit does not take effect until all those approvals have been granted.

While not previously subject to legal proceedings, section 53(4) of the LUPA Act has traditionally been interpreted as ensuring that use or development does not commence until all required approvals have been secured.

On 26 June 2026, the Magistrate’s decision interpreted section 53(4) of the LUPA Act as meaning that if another approval is required for a use or development, the permit, as a whole, does not take effect.

The ruling has implications for the operation of planning permits and the broader planning system. For example, some approvals can only be obtained after construction has been completed, such as an occupancy permit under the Building Act 2016 or the approval of a final plan of subdivision under the Local Government (Building and Miscellaneous Provisions) Act 1993. However, under the interpretation adopted in the Magistrate’s decision, the planning permit does not take effect until all relevant approvals have been obtained, thereby preventing construction from commencing in the first place.

Provisions similar to section 53(4) of the LUPA Act apply to a major project permit (section 60ZZS of the LUPA Act) and a permit issued in combination with a Local Provisions Schedule (LPS) amendment (section 42C of the LUPA Act). The Bill also modifies these provisions to allow a permit to be in effect prior to obtaining all approvals.

The draft Bill also addresses sections 53(6) and 42C(1)(d) of the LUPA Act which has a similar issue stating that a permit requiring a Part 5 Agreement does not take effect until that agreement has been executed. This creates uncertainty in the operation of the permit, increasing the risk of legal challenge.

Finally, the draft Bill inserts savings provisions after section 87H of the LUPA Act to ensure that there is no uncertainty regarding the status of existing permits affected by the amendments outlined above. The provisions clarify that such permits are taken to be in effect, irrespective of whether all approvals required under the LUPA Act or any other Act in relation to the authorised use or development have been obtained.

Lifecycle

Proposed amendment, Status: Complete

The draft Bill proposes amendments to the Land Use Planning and Approvals Act 1993.

The Background section above provides an overview of the proposed amendment.

A copy of the draft Bill and a more detailed Background Report can be found under the 'Have Your Say' tab below.

Have your say, Status: Current

The draft Bill is open for public consultation.

The draft Bill and supporting documents are available below.

Consultation will be open from Monday, 16 November 2026 and concluding 5pm Friday,
15 January 2027
.

You can have your say by making a written submission and posting or emailing it to our office before the consultation period closes.

Your personal information - submission publication

Postal address

State Planning Office
Building Tasmania
GPO Box 536
Hobart TAS 7001

Email address

haveyoursay@stateplanning.tas.gov.au

Review of submissions, Status: Not started

Once complete, all submissions will be reviewed and considered by the Minister before the revised draft Land Use Planning and Appeals (taking effect of permit) Bill 2026 is tabled in Parliament.

Consultation report released, Status: Not started

A report on the submissions received will be prepared and released.

Bill goes before Parliament, Status: Not started

The draft Bill will be tabled and debated in Parliament in 2027 and if approved will take effect soon after.